|
|
|
|
As the largest of the Enchanted Forest's show venues, the Great Arena
was also the largest earth moving project in the park. To create the
raked seating large hills were formed first to create the profile of
the seating areas. |
|
|
|
|
|
|
|
Truck after truck of fill was brought in to create the earthen berm. Bulldozers and steam rollers then moved and compacted the soil in
preparation for the next phases of construction. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
With the terraced walkways around the Arena in place and the slope of
the hills set to specifications, the concrete work began. First along
the edges of the Arena floor, foundation walls were poured. These would
sever as support for the tiered concrete seating areas and arena steps, as well
as create the wall around the Arena's floor. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
With the foundation walls set, the wooden forms and rebar were built up
section by section. The concrete forms were then filled using a pumper
truck from the floor level. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Over the weeks the concrete sections took shape, eventually surrounding
the Arena completely. Once the lower level terraces were complete, the
crews started forming the upper tiers of seating. While the concrete
work was still going on for the upper level, installation of the
aluminum benches began. The seats were installed first, then the
colorful bench backs were placed. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
As opening day approached, work on the Arena went into high gear as
crews tried to finish construction. The Great Arena was ready for the
July 1st opening day of the park though the surrounding Rootin' Tootin'
Rip Roarin' area of the park wasn't completed. For the first three days
the park was open guests would have to trek through the construction
area to the Great Arena to see the spectacular shows. |
|
|
|
|
|
|
|