Wooden roller coasters have been a cornerstone of amusement parks and
theme parks for more than 100 years, and over that time there have been
very few changes in their technology. That is until the dawn of the twenty first
century when INTAMIN developed a new system for prefabricating the
components of a wood coaster creating a smoother, faster, more
dynamic ride.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
In 2005, with the
opening of Kingda Ka just having taken place, an announcement was made
that the ten year old Viper roller coaster was being removed, however, there
was no announcement of what would be replacing it. Along with the
removal of Viper, the surrounding area began to show the markings of a
big new construction project. The fan community quickly began
circulating rumors of a major new coaster but the rumors were dismissed
as fantasy coming on the heels of the world record breaking addition of Kingda Ka and the
Golden Kingdom.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Trees all around the area were
marked for removal along with a stand of trees in the infield of Rolling
Thunder. It quickly became apparent that something big was on its way.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
With Viper cleared
except for the preserved station, it quickly became apparent the plan was
to re-use the southwestern themed structure as part of the new (and
still unannounced) attraction. As the summer went on the trees were
cleared from the area around Rolling Thunder, with site preparation
happening in several areas that were inaccessible to guests. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
With all of parts and
debris of the former Viper
cleared, markings began appearing for new construction. Rebar frames
were beginning to be fabricated as the initial steps of creating footings
for a new attraction commenced. Construction trailers and other equipment began to
show up on site as well.
While site preparation was still
happening inside the park and no announcements had yet been made about
what was coming, the construction area in the parking lot that had
served as the delivery area for Kingda Ka's parts began to receive
shipments of materials. With the arrival of the first prefabricated
wooden rails, the cat was out of the bag and it quickly became obvious
that Great Adventure was building a new INTAMIN prefabricated wood
coaster, but the debate raged on as to how big and what the layout would
be right up until the day the announcement was made. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
With the arrival of
Labor Day, the area from the bridge near the Northern Star Arena to the
Taz Tornado (Rotor) ride was closed off completely and disassembly of the
rides and existing structures began. The first of the rides to be
removed was the Rodeo Stampede which was carefully taken apart for
relocation to Six Flags Over Texas.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Taz Tornado was
also removed as part of preparation for the new roller coaster. The
Rotor had been relocated twice before while at Great Adventure, but this
time it was not to be and the ride was scrapped as it was removed.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
A third ride was
removed from the area as well, and in this case it was the Tweety
Carousel that had just been relocated for 2005 when its Bugs Bunny Land
home was demolished to make way for the Golden Kingdom. The kiddie
carousel would be relocated once again for the 2006 season to park's
other major addition for the upcoming year, Bugs Bunny National Park.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
While more coaster
parts continued to arrive in the parking lot staging area, site
preparations went on inside the park with the fixtures and equipment
being removed from the buildings slated for demolition. The area
was cleared of the Dry Gulch Shooting Gallery (formerly Los Sombreros), Pedro's Pitch games
structure, a fountain, and a waffle cones stand. In addition, the
facades of the "ghost town" that served as the queue for the Viper were
also removed.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Key El Toro Technical
Specifications |
Click the image below to watch
a promotional video for El Toro |
Maximum Speed: 70 mph
Lift Height: 188 feet
First Drop Angle: 76 degrees
First Drop Length: 176 feet
Ride Time: 1 min 42 sec
Track Length: 4400 feet
Number of Trains: 2
Passengers Per Train: 36
Ride Capacity: 1500 per hour |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
At the end of
September the announcement was finally made, and El Toro was unveiled as
the centerpiece of the brand new Plaza del Carnaval area of the park
which would debut for the 2006 season. This would be the second record
breaking coaster and the second newly themed area added to Great
Adventure in two years. This was all part of a planned five year
reimagining of the park that would have improved and updated all of the
areas. That plan would change after just two years with the changes in
corporate management and the financial situation of Six Flags. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
As the 2005 season began to draw to a close, construction really went
into full swing with footers being poured quickly to beat the winter
weather. Demolition of the remaining structures and walkways was taking
place as the parts for the massive new coaster continued to
arrive from Europe. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The following are the October entries from Great
Adventure's official construction journal on their website:
Oct. 12 -
At the end of September, construction started and we began to
establish the footprint of the ride, identifying the exact
locations for the foundations and the sequence in which they
would be installed. Excavation began and reinforcing bars were
placed in the footings and concrete was subsequently poured. So
far we poured approximately 20 footings and 20 piers with anchor
bolts.
At the present
time, we are fabricating the “bents” on site – bents are what
the track sits on; and lumber that will be assembled on location
is being sized, cut, labeled, drilled and packaged at a mill in
Germany. The goal is to finish concrete work in phase one, two
and three which includes the lift structure, in and out of the
station, and the first drop, in a timely matter so we can begin
wood erection. A challenge lately has been the excessive amount
of rainwater we have to pump out so we can continue our
progress.
Update from Richard Beane – Site
Superintendent
Oct. 19 -
This past weekend, we completed topography and tree markings for
the new childrens' section – Bugs Bunny National Park - and
confirmed the final layout and placement for the childrens'
rides. We also began excavation for the top of the lift footings
and assembled more than 30 bents.
Update from Al Rubano – Director
of Construction
Oct. 24-
The past two days we've poured concrete for the lift footings
and pier caps and continue to fabricate bents for the lift area.
Update from Al Rubano – Director
of Construction
Oct. 28 -
The construction of El Toro continues to move along at a steady
pace. With the majority of footings, concrete pier caps and
anchor bolt placement substantially complete for the lift, we
are focused on the concrete footing pour for the crest of the
lift hill to the return drop. More than 400 yards of concrete,
equal to 40 truck loads, will be needed to fill the enormous
area supporting the return at the top of the lift hill.
Portions of the track and lumber for El Toro continue to arrive
weekly. The lumber for the lift area is staged in the parking
area next to Kingda Ka. Approximately 40 two-legged bents have
been fabricated. The bent assembly carpenter crew is in the
process of bundling up components for three-legged bents for
transport and staging in the lift area for assembly on site.
Erection starting at the base of the lift will begin on or
before Mon., Oct. 31, 2005.
Update from Al Rubano – Director
of Construction
|
By the final weekend of the 2005 season, the first bents were in
place and El Toro had officially began vertical construction.
These are the November & December entries from Great
Adventure's official construction journal on their website:
Nov. 3 -
The major concrete pour was completed for the lift hill Oct. 28.
With the footings for the lift hill and return drop in place,
form work to complete the setting of anchor bolts and pier caps
follows. The first bent frame was erected Oct. 28. Eleven bents
are currently in place. With the mild Nov. weather we’re
experiencing, we expect to make a significant progress by week’s
end. Clearing for Plaza del Carnaval continues with the removal
of 54,000 sq. ft. of concrete walkway and site grading. We are
currently preparing the area along Lahaway Creek. This section
will consist of approximately 35% of the track for El Toro.
For the next several weeks will focus on lift erection and
footing for the return track adjacent to the lift and along
Lahaway Creek.
Update from Al Rubano – Director
of Construction
Nov. 11 -
The construction of El Toro continues moving forward. The mild
November weather has been in our favor and enabled us to
accomplish a lot over the last week. The lift hill has been
assembled to a height of about 75 feet and several sections of
track along the bottom of the lift hill are in place. Assembly
and erection will continue throughout the weekend. We have
excavated footings for the bents extending along the Lahaway
Creek. Footings for the bottom of the return drop have been
excavated in preparation to be formed. Al
Rubano – Director of Construction
Nov. 18 -
The foundation work continues from the drop adjacent to the
station, heading south along Lahaway Creek. Gang footings have
been poured behind La Cantina and at the hairpin turn where the
ride heads back along the creek, past the station to where it
crosses over Rolling Thunder. Bent erection at the lift hill
continues, rising past the height of 110 feet, heading to the
188 foot goal.
Nov. 23 -
Foundation work and bent erection continues this week. We'll
break for turkey on Thanksgiving and return Friday to pick up
where we left off.
Have a Happy Thanksgiving!
Dec. 2-
Bent erection on the lift hill continues at a steady pace. With
the erection of bents 48 and 49 we should reach a height of 164
feet by the end of this week. The 188-foot height for the lift
should be completed by Christmas.
Al Rubano - Director of
Construction
Dec. 8-
“Nor Hail, Rain, Sleet or Snow.” Regardless of the weather
conditions we continue to move forward on a daily basis.
Addressing the challenges of winter weather, especially snow
removal, Six Flags workers start each day with plows, shovels
and brooms to remove the snow, allowing them to continue to
work. The erection of the bent frames is occasionally hampered
by high winds and for worker safety, work must be held up.
A 380-yard concrete pour was completed for the footwork
under the top of the hairpin turn. Bent erection is complete to
column line 60 at approximately 164 feet. Columns 49-52 are
erected to the 97-foot elevation. Bent erection continues to
top-out at column line 62 at the 188-foot elevation before the
end of the year.
Construction of the support services and
ride photo buildings, merchandise kiosk and restaurant
renovations will begin before the holidays.
Al Rubano - Director of
Construction
Dec. 17-
- Construction on El Toro continues to move along at a steady
pace. The goal of topping-off the lift is right on schedule.
Weather permitting, the top bent will be positioned at the
188-foot height Tues., Dec. 20. We are also focusing on the
steel fabrication work for station modifications as well as
continuing foundation and pier work.
Now that we have the
permits for the ride photo building, merchandise shop and
restaurant, work will begin in those areas on or before the
first of January.
Wishing everyone a very,
happy holiday season!
Al Rubano - Director of
Construction
Dec. 20
Park Completes Towering Lift
Hill of ‘El Toro’
The
construction team at Six Flags Great Adventure today reached an
important milestone in the erection of El Toro. After placing
the top portion of the 188-foot-tall wooden track support slowly
and carefully into position, El Toro now ranks as the second
tallest wooden coaster in America, and the third tallest in the
world.
This 188-foot-tall support is known as “bent 55”
of 613 total bents Fun facts about bent 55 • 208
boards of lumber • 192 bolts • Each bolt measures 24 mm x
440 mm • 22,500 lbs. • 34.5 feet wide at the base Bent 55 is separated into two sections, a top and a bottom.
The “topping off” piece is the bent’s top section Fun
facts about bent 55’s top section • 87.5 ft. tall • 19.8
ft. wide at the splice • 56 boards of lumber • 7,500 lbs.,
placed on top of a 15,000-lb. base The crane lifting bent
55’s top portion is 260 ft. tall.
Approximately 10
workers climb bent 55’s top portion to secure it to the
structure.
Temporary bracing of bent 55’s top portion
takes approximately 2 to 3 hours
Al Rubano - Director of
Construction & Richard Beane – Site Superintendent
Dec. 28 -
On Dec. 20 the lift hill was topped off at 188 feet. We
are now focused on bent assembly for the hairpin turn at the top
of the lift hill to the first drop. Massive bents will be
assembled on the ground, lifted and set in place to an erected
height of 187 feet.
The winch drum for the cable and catch
car system has been set. As we move forward, we are in the
process of setting up a separate lift-detail gang to focus on El
Toro’s track and mechanical assembly.
Work continues at a steady pace throughout the area. Last week
a concrete pour for the station bent footings was complete.
During this last week of 2005, excavation work in the Plaza del
Carnaval section will continue from the return at the top of the
lift to La Cocina restaurant.
Al Rubano, Director of
Construction |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
These are the entries from Great
Adventure's official construction journal on their website: |
January: |
February: |
March: |
Jan. 6, 2006 -
Despite recent inclement weather, progress continues for the erection of
El Toro's supports and track placement. Earlier this week, column 58 was
topped off at 188 feet. We are currently at a height of 97 feet through
column 63. Column 63 is the area where the track starts to turn between
the lift hill and the first drop.
Phase 1, 2 and 3 of ride
foundations at the lift and station area are substantially complete.
Phase 4 foundations which run along the Lahaway Creek, then makes the
turn behind Wildside Pizza is 65% complete. Engineering for the final
foundation phases 5 and 6 have been completed and are in fabrication for
reinforcing.
Al Rubano, Director of Construction
Jan. 12, 2006 With
the mild weather we’re experiencing in central New Jersey, the size of
El Toro’s massive structure increases daily. Over the last couple days,
the first bent in the curve at the top of the lift hill (#63) was
erected to completion.
Workers are busy throughout the entire
construction site. The electrical underground conduit, which will run
the motor control room, is nearly 40% completed. Storm sewer and
sanitary relocation will be starting soon along with installation of the
underground air lines necessary for the ride’s braking system.
The layout for Phase 5 foundation work has been started. Phase 5 is the
area inside Rolling Thunder’s track where El Toro crosses over and
continues along Rolling Thunder’s return track .
Richard Beane, General Construction
Supervisor
Jan. 19, 2006 The
high winds and rain this week were definitely a challenge. We continued
erection to bent 65 at the curve of the lift hill. We started erection
at column lines 101 to 107 which runs parallel with the station pass the
invert of the first drop. Foundation will continue through phase four
and layout continues for phase five and six.
Al Rubano, Director of Construction
Jan. 27, 2006 This
week we continued framing of the hairpin turn at the top of the lift. To
keep the job moving we are working on various sections of the coaster.
We continued erection up to columns 115. We are assembling bents for
column line 137, which is heading south along Lahaway Creek.
Al Rubano, Director of Construction |
Feb. 4, 2006 We've
had a great start to phase 5 and 6, although we tend to loose one day of
work a week due to inclement weather. We erected 188 feet to bent line
71 and erected from column lines 99 to 115 and 141 to 166. We
substantially completed phase 1, 2 and 3 and are approximately 95
percent complete with phase 4. We began installation of underground
conduit on the motor control center to the base of the lift continuing
to the top of the lift as well as the safety rigs located in the
cross-over section of phase 5 and 6.
Al Rubano, Director of Construction
Feb. 10, 2006 Work
continues at a normal pace with the exception of three rain days last
week. We erected to bent line 73 and erected from column lines 116 to
118 and 167 to 170. Framing for the station unload deck is complete and
we started framing for the station loading deck. The installation of
underground conduit on the motor control center to the base of the lift
continuing to the top of the lift and safety rigs in the crossover
section are substantially complete.
Things are moving along.
Al Rubano, Director of
Construction
Feb. 17, 2006 After
loosing two days for snow removal, we continued to move forward and
erected to the top of column line 76. We now completed the hairpin turn
at the top of the lift. Fabrication of bent 77 and 78 are in progress.
We have approximately 20 percent completed in phase 5 and 6.
Al Rubano, Director of
Construction
Feb. 24, 2006 Work
continues on El Toro through column line 80. We have approximately 35
percent completed in phase 5 and 6.
Al Rubano, Director of Construction |
March 3, 2006 We
continued erection through column line 83, column lines 99 through 136
and 138 through 176. The reason we break-up erection into sections is to
allow for site access. We also erected through the station and continued
into the hairpin turn outside the station.
Al Rubano, Director of Construction
March 10, 2006 We
erected to column line 93. Bents 94, 95, 96, 97, 98, and 131, 132, 133,
and 137 are built and ready for installation.
Al Rubano, Director of Construction
March 17, 2006 The
station deck is poured and we began framing for the interior motor
control center in the station. We continued detailing and installing
ribbon boards, diagonal bracing, walk boards and laminated track.
Erection is complete through column line 219 entering the hairpin turn.
The mechanical drive is ready for installation on the lift. Phase 5 and
6 are approximately 65 percent complete.
Al Rubano, Director of Construction
March 24, 2006 Construction
on El Toro continues to march forward aggressively for opening. The
trains arrived and will soon go through inspection prior to
installation. Al Rubano,
Director of Construction
|
|
|
|
|
With the opening of the 2006 season on March 31st, El Toro was
still very much a work in progress. The harsh winter weather combined
with uncertainties caused by changes in Six Flags corporate management as
well as park level management complicated construction.
The
company's new CEO wanted to take Six Flags in a new direction, catering
more towards families and less to thrill seekers and made it quite plain that
El Toro and the other major coasters being built at Six Flags parks that
year would be the last major coasters added for many years to come.
Ironically, that same CEO often cited El Toro as the best roller coaster
in any park. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
apr1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The huge wooden structure would forever change the skyline of Great
Adventure. The new coaster towered high above the trees and was
an immediate visual draw down to the formerly quiet end of the park
even while construction was still taking place. |
|
|
|
|
|
April 8, 2006 The
race is on for Six Flags Great Adventure and the opening of El Toro.
Construction is moving along at a rapid pace.
By the end of this
weekend we will close bent sections 85-88 and 133-137 at the hairpin
where the train leaves the station and also the bridge section 176-179,
which is the access point to the walkway along Layaway creek. We have
roughly 35 bents remaining that will complete the hairpin turn in the
Plaza del Carnaval area.
Keep a watchful eye on the next few
weeks, because construction is moving quickly.
Al Rubano, Director of Construction |
|
apr9 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Piece by piece the structure came together. Each piece was sent from the
factory in Europe pre-cut, pre-drilled and numbered and assembled like a
giant Erector set. |
|
|
|
|
|
|
|
|
|
|
|
Each week more of the coaster came together with the
support structure going up first and the rails being installed section
by section as the structure was topped off.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
As April came to a close El Toro began to look closer to completion.
The bulk of the structure was up and much of the track was in place as
the huge new coaster neared opening day. The goal was to get the ride
open in time for Memorial Day weekend and the kickoff of the busy summer
season.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
As May went on the mechanical systems became the focus
while the structure was completed. The cable lift system was a fairly
unique feature on a coaster, especially a wood coaster. Other INTAMIN
coasters featuring cable lift systems had the train engage the lift
directly from the station, while El Toro would leave the station and
engage the lift with the trains already in motion. The reliability of
the cable lift and its proper functioning were a big question mark for
many enthusiasts while the construction was still underway.
While the crews were working hard to get El Toro finished in
time for Memorial Day, things took just a little longer than anticipated and at the
beginning of June the coaster still was not quite ready to open.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
During the first week of June test runs began as the crews began to
cycle the trains. Water dummies were the first passengers to get to
experience El Toro, completing lap after lap on the new coaster. A
big part of the test process involved testing and adjusting the lift
hill mechanism.
In the mean time,
the crews were hard at work below on the ride's queue area as well as
the support facilities like the photo booth in preparation for the
coaster's debut. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
El Toro not only used the station
building from
Viper but the old coaster's entry portal as well. The archway which had
once featured the Viper logo was fitted with the new El Toro logo.
As the countdown to opening continued other features such as a sculpture of a bull
and a set of
test seats were added inside the entry plaza of the ride. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
On June 11th, the first riders got to experience El Toro as the park
prepared for the ride's opening day. These first riders were there to
film the "B-roll" footage supplied to the news media as part of the
coaster's official debut. |
|
|
|
|
jun17 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Finally, El Toro made its debut to the general public on June 12, 2006, becoming an
immediate success. Being the first INTAMIN prefabricated wooden coaster
in North America brought enthusiasts from far and wide to try it out and
experience the amazingly smooth ride. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The crowds loved El Toro, drawing huge lines of guests. Great
Adventure's one two punch of the record breaking Kingda Ka and El Toro
made the park a destination for thrill seekers and coaster enthusiasts
from all around the country and around the world. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
El Toro began its second season in 2007 with new sponsorship
posters. As
part of the new Six Flags management's approach to improving their
finances, they emphasized sponsorships and in-park advertising. Guests
in a queue were a captive audience, so it made sense to advertise to
them while waiting in line.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
In the seasons since El Toro opened the only real changes
that have occurred have been the weathering of the wooden structure and
the trains being wrapped in advertising. Those aesthetic changes have
done nothing to diminish the ride experience, with El Toro delivering
high speed thrills and lots of "air time".
One
of the oddest controversies among coaster enthusiasts regarding El Toro
has been over whether or not it can be considered a "true" wooden roller
coaster. The feeling among some purists is that the prefabricated wooden
rails are a cheat. At the same time, many of the same enthusiasts see
other wooden roller coasters which utilize a steel support structure as
being "true" wooden coasters since the rails are fabricated from lumber
on site. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The coaster's reputation has only
grown over time, consistently ranked as one of the world's best wooden
coasters. The ride has even taken the number one position on annual
polls of enthusiasts. Other wooden coasters have been built since then,
and so far none has been able to surpass El Toro. Not even a newer
post-El toro INTAMIN prefabricated coaster with a taller and steeper
drop was able to beat Great Adventure's legenday bull - El Toro! |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Construction Log Photos from |
|
|
|
Six Flags Great Adventure's Web Page |
|
|
|
All images below courtesy of Six Flags
Great Adventure.
Clicking on the images below will not result in a larger image. |
|
|
|
|
|
|
Sept 26, 2005 |
Sept 28, 2005 |
Sept 30, 2005 |
|
|
|
|
|
|
Oct 3, 2005 |
Oct 7, 2005 |
Oct 21, 2005 |
|
|
|
|
|
|
Oct 21, 2005 |
Oct 21, 2005 |
Oct 28, 2005 |
|
|
|
|
|
|
Oct 28, 2005 |
Oct 28, 2005 |
Oct 28, 2005 |
|
|
|
|
|
|
Oct 28, 2005 |
Oct 28, 2005 |
Oct 31, 2005 |
|
|
|
|
|
|
Nov 1, 2005 |
Nov 1, 2005 |
Nov 2, 2005 |
|
|
|
|
|
|
Nov 5, 2005 |
Nov 7, 2005 |
Nov 8, 2005 |
|
|
|
|
|
|
Nov 10, 2005 |
Nov 10, 2005 |
Nov 5, 2005 |
|
|
|
|
|
|
Nov 18, 2005 |
Nov 18, 2005 |
Nov 19, 2005 |
|
|
|
|
|
|
Nov 23, 2005 |
Nov 26, 2005 |
Nov 28, 2005 |
|
|
|
|
|
|
Nov 29, 2005 |
Dec 5, 2005 |
Dec 6, 2005 |
|
|
|
|
|
|
Dec 6, 2005 |
Dec 8, 2005 |
Dec 8, 2005 |
|
|
|
|
|
|
Dec 13, 2005 |
Dec 14, 2005 |
Dec 16, 2005 |
|
|
|
|
|
|
Dec 20, 2005 |
Dec 20, 2005 |
Dec 20, 2005 |
|
|
|
|
|
|
Dec 20, 2005 |
Dec 29, 2005 |
Dec 29, 2005 |
|
|
|
|
|
|
Dec 29, 2005 |
Dec 29, 2005 |
Jan 4, 2006 |
|
|
|
|
|
|
Jan 4, 2006 |
Jan 6, 2006 |
Jan 6, 2006 |
|
|
|
|
|
|
Jan 11, 2006 |
Jan 11, 2006 |
Jan 12, 2006 |
|
|
|
|
|
|
Jan 19, 2006 |
Jan 19, 2006 |
Jan 19, 2006 |
|
|
|
|
|
|
Jan 27, 2006 |
Jan 27, 2006 |
Feb 3, 2006 |
|
|
|
|
|
|
Feb 3, 2006 |
Feb 10, 2006 |
Feb 10, 2006 |
|
|
|
|
|
|
Feb 17, 2006 |
Feb 17, 2006 |
Feb 24, 2006 |
|
|
|
|
|
|
March 2, 2006 |
March 10, 2006 |
March 10, 2006 |
|
|
|
|
|
|
March 17, 2006 |
March 24, 2006 |
March 30, 2006 |
|
|
|
|
|
|
March 30, 2006 |
April 8, 2006 |
April 8, 2006 |
|
|
|
|
|
|
April 14, 2006 |
April 14, 2006 |
April 14, 2006 |
|
|
|
|
|
|
April 22, 2006 |
April 22, 2006 |
April 29, 2006 |
|
|
|
|
|
|
May 6, 2006 |
May 6, 2006 |
May 14, 2006 |
|
|
|
|
|
|
May 14, 2006 |
May 20, 2006 |
May 20, 2006 |
|
|
|
|
|
|
May 28, 2006 |
May 28, 2006 |
May 28, 2006 |
|
|
|
|
|
|
|
|
|
|
El Toro
Souvenirs |
|
|
|
|
|
|
|
|
|
|